This article will help you learn all about the planning approvals processes in Western Australia, for subdividing and developing residential Property. It’s important to get your head around the panning approvals processes, as there is a fair bit that needs to happen before you are turning a sod of earth on site. For developing property in WA, approvals happen in two distinct stages. The first set of controls that your development is a assessed against is Planning Controls, covering things like % of site coverage, lot area and dimensions, setbacks, building height, overshadowing, visual privacy, passive surveillance, garden area and landscaping, external appearance etc.
The second set of controls that your development plans are assessed against, after planning approvals are to hand, is the relevant sections of the BCA/NCC relative to your class of building. These acronyms are short for the Building Code of Australia and National Construction Code. An interest at this stage is taken in the build technology that is going to bring you designs to like: engineering details, materials, energy efficiency ratings, glazing, specifications, etc.
You need to get planning approvals first; one for the subdivision (if applicable), and the second one for built form that goes on the site. Then, you will need to get a build permit, for applicable works that need it, such as new single house and grouped dwellings (the built form component), or retaining over 500mm in height and modifications to existing dwellings (the subdivision component). Let’s look at planning controls in a bit more detail.Â
Dwelling Planning Approval (DA)
The decision maker for planning approvals for dwellings in the Local government. They are delegated authority under the PDA (planning and development act) to assess plans and make determinations accordingly. They will assess your plans against:
- The R-codes of Western Australia (relevant sections).
- Their local town planning scheme.
- Relevant local planning policies and provisions that are endorsed by the state planning commission that supersede, override and or compliment the baseline provisions in the Rcodes.
Statutory timeframes aside, the reality is a DA is typically to hand in 4-6 months from the date of lodgment, considering time for RFI’s and public advertising (where applicable). This depends on the complexity of the application and local government workload; in some instances, it can take longer. Preparing a DA set, from point of design brief, concept development, review and lodgment, usually takes 2-4 months. Once approved, an approval is valid for 2 years from date of issue.
Note: you do not lodge a DA for land subdivision, local government is delegated no authority to make these determinations. This is handled by the Western Australian Planning Commission (WAPC) in a separate application. Same site, two separate applications. In some instances, particularly in some dual coded areas of certain local governments, it is necessary to obtain planning approval first (DA) before an approval for subdivision can be sought (they take an interest in the built form outcome first before endorsing subdivision during WAPC referral ). You will also need a DA in hand (or at least underway) for special purpose dwellings, such as single bed dwellings , aged dependent persons dwellings, small dwellings and accessible dwellings ( relative to parts B or C of the Rcodes).Â
Subdivision Planning Approval (1A)
The decision maker for subdivision planning approvals is the Western Australian Planning Commission (WAPC). They handle all applications for Green title ( freehold) and Survey Strata title ( land area based Strata ) applications in WA. They handle the application as the key decision maker, sending it to referral agencies during the assessment period (3 months), like the local government in which the subject site is located, Watercorp, western power, Atco gas, etc. These agencies provide comment and the WAPC considers them, compiling either a list of conditions for the applicant in a conditional approval , or a refusal.
The statutory timeframe for a determination is 90 days from the date of lodgment, and is honored quite consistently by the WAPC. In some instances (such as for complex, some rural and some larger subdivisions), larger referral agencies and accompanying reporting may increase this timeframe, particularly when agencies such as DFES (for bushfire panning), department of health or water ( for SSE or site soil evaluation, for sewerage management ) or Department of environment (for flora and fauna survey and environmental concerns) get involved.
A conditional subdivision approval usually takes no more than 3 or 4 weeks to prepare and lodge (unless supplemental reports like bushfire planning or environmental surveys are required) is valid for 3 years from date of issue.
You can learn more about approvals processes, planning, design and the Rcodes in our online books and courses
To discuss subdivision and planning approvals in Western Australia and the best ways to develop a property, contact us and we can get in touch to discuss